Project Network Planning Assignment
Project Networking provides the necessary tools to monitor project progress. Considerable time and effort is expended developing successful project networks.
Refer to exercise 9 in chapter 6 of the textbook. Read the assignment thoroughly and analyze the data provided in the diagram.
Compute the project network sequence and proper timing to complete the project using an excel spreadsheet, PowerPoint, or another appropriate form of delivery method. Address all required information in the description presented in exercise 9. In addition, respond to the following questions (300-500 words):
APA format is not required, but solid academic writing is expected. Include at least two properly cited academic sources to support your facts. This exercise is worth 30 points.
Project Network Planning Assignment
Exercise 9
You are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities.
ID Description Predecessor Time (days)
A Systems design None 2
B Subsystem A design A 1
C Subsystem B design A 1
D Subsystem C design A 1
E Program A B 2
F Program B C 2
G Program C D 2
H Subsystem A test E 1
I Subsystem B test F 1
J Subsystem C test G 1
K Integration H, I, J 3
L Integration test K 1